Temporary Overhead Installation

Please make a note of vertical clearance requirements for each type of service. Permanent service poles are the property of Lane Electric. Lane Electric will install and maintain the poles and guy wires.

Temporary-Overhead-Installation

Requirements:

  1. Temporary pole should be located 10’ – 20’ from transformer pole or as specified by the Cooperative.
  2. Consumer shall supply temporary pole, meter base, mast with weather head, main disconnect, and grounds to National Electric Code (NEC) construction code specifications.
  3. The Cooperative will provide maximum 20’ service drop and install meter.
  4. Energizing of consumer’s service is contingent upon an approved State or City electrical inspection.
  5. Before you dig, call the Utility Notification Center at 811 or 1-800-332-2344, 48 hours in advance.